Las Sendas

PROJECT UPDATES

There's always something happening at Las Sendas — see the status of various projects the Association is working on around the community right here.
Playground Shades
Playground Shades
 
Shade for the Trailhead and Sonoran Heights playgrounds was approved in 2020 along with the proposal for the new equipment. After multiple delays for a variety of reasons, the shade structures were finally installed the week of November 22. Our landscape contractor will restore the surrounding turf over the next several weeks. Thank you for your patience!
 
Last updated November 29, 2021.
Fire Mitigation
Fire Mitigation
 
DLC Resources is performing fire mitigation in some of our common areas. The work began on August 23 and will take about four months to complete. The following enclaves are scheduled for 2021:
  • Sonoran Hills - Done
  • Founders Ranch - Done
  • Mountain Village - Done
  • Terraces - Done
  • Silverhawk - In Progres
  • Grayfox - In Progres
  • Windsong
  • Pinnacle Hills - Deferred
For more information about Las Sendas' fire mitigation plans, the Firewise USA designation, and what you can do to protect your property, click here.
 
Last updated November 29, 2021.
Post Tension Tennis Courts
Post Tension Tennis Courts
 
Post-tension tennis courts have been installed on courts 3, 4, and 5 at the Sonoran Hills Tennis Club.  All of the courts are now open and operational! Some additional work is still needed, including:
•    Lights being reconnected
•    Wheelchair ramps to be installed
•    Paint touch-ups and cleanup
•    Windscreen installation
 
Some one-day closure may be necessary to complete the above and other tasks.  We will notify you if your reservations need to be rescheduled. 

Post-tension concrete courts will resist and prevent cracking, thanks to pre-stressed steel tendons below the surface. These upgraded courts will provide Las Sendas with a sturdy and durable playing surface that can withstand the rigors of consistent use.

Court six at Sonoran Hills Tennis Club and courts one and two at the Trailhead will be upgraded in 2022.
 
 
Last updated September 14, 2021.
Vehicle Gate
Vehicle Gate Component Project
 
Every enclave is scheduled to receive new, more secure gates that can be opened by a sticker on your headlight, called an RFID tag. The schedule for this project will change occasionally — you can view the updated gate schedule here.
 
Here are some additional helpful links:
 
Last updated September 17, 2021.
New Amenity Access Cards
New Amenity Access Cards
 
New and more secure amenity access cards are here, and our system is live!
 
 
Last updated June 29, 2021.
City of Mesa
Sewer Manhole Access Project + Closed Trails
 
The City of Mesa Engineering department has informed us that a ten-foot-wide dirt utility access road will be built outside the western edge of our community, just north of Thomas Road and parallel to Power Road. Work will begin this month and last approximately three months. 
Talis Construction will be clearing some existing vegetation and constructing a stabilized dirt access road with drainage crossings to prohibit dust and erosion. This path will provide City utility crews access to existing utility holes for periodic cleaning and maintenance. Work will take place during daytime hours, and you may hear some related construction noise. 
 
During construction, the existing trail and access points from the neighborhood will be temporarily closed. Please do not attempt to walk, run or bike in this area until improvements are complete and barricades removed! Please adhere to this temporary closure for your safety.
 
If you have any questions or concerns about this project, please contact Curt Albright or Michele Arrollado with the City of Mesa Engineering Public Relations Department at 480-644-3800. You can also reach Talis Construction via their project hotline at 480-532-5588.
 
 
Last updated October 20, 2021.
Asphalt Work
Asphalt Repair and Reconstruction
 
The 2021 road repairs, crack filling, reconstruction and seal coating work is complete.
 
 
Last updated October 20, 2021.
New Mailboxes
New Mailboxes
 
This fall, seven more enclaves will be receiving brand new, more secure mailboxes. Below are the tentative installation dates for the remainder of this year's project. If your mailbox is being replaced, you'll receive a letter via USPS and an email in advance.
 
  • Grayfox — DONE August 27
  • Rolling Hills — DONE September 16 & 18
  • Silverhawke — DONE November 5 and 6                              
  • Sonoran Heights — DONE November 13 
  • Sonoran Hills — DONE September 25
  • The Highlands — DONE October 28 & 30
  • The Terraces — DONE November 12 
 
Last updated November 29, 2021.
Tree Trimming
Enclave Tree Trimming
 
Tree Trimming within the enclaves ("behind the gates") has been completed.  ProQual will begin other tree trimming in 2022.
 
Last updated November 29, 2021.
Common Area Wall Painting
Common Area Wall Painting
 
After obtaining bids for the 2021 painting project, we learned that current prices are significantly higher than budgeted. Not only do these costs affect payments from the Association's reserve account, but they also affect homeowners directly, since residents are responsible for reimbursing the Association 50% of the cost to paint the wrought iron on their walls (where applicable). At the June 24 meeting, the Board decided to defer the 2021 painting project until 2022 or until costs go down.
 
Once the Board decides to move forward on this project again, the common area walls for the following enclaves will be scheduled to be repainted:
  • Black Rock
  • Legacy Hills
  • Mountain Gate
  • Stonecliff
  • Trailridge
  • Preserve
  • Pinnacle Hills  
  • Golf Colony
  • Granite Preserve
 
Last updated July 2, 2021.
Looking for something else? Feel free to give us a call during regular business hours at 480-357-8780.