Las Sendas

PROJECT UPDATES

There's always something happening at Las Sendas — see the status of various projects the Association is working on around the community right here.
Vehicle Gate
Vehicle Gate Component Project
 
Every enclave is scheduled to receive new, more secure gates that can be opened by a sticker on your headlight, called an RFID tag. The schedule for this project will change occasionally — you can view the updated gate schedule here.
 
Here are some additional helpful links:
 
Last updated May 4, 2021.
Post Tension Tennis Courts
Post Tension Tennis Courts
 
Our contractor, General Acrylics, has scheduled the installation of some post-tension tennis courts for this summer. This work began on July 12, 2021, and will take approximately two months to complete.

Post-tension concrete courts will resist and prevent cracking, thanks to pre-stressed steel tendons below the surface. These upgraded courts will provide Las Sendas with a sturdy and durable playing surface that can withstand the rigors of consistent use.

During the installation, courts three, four, and five at the Sonoran Hills Tennis Club (at Boulder Mountain Parke) will be closed.
 
Due to high temperatures during the day, crews will be pouring concrete overnight. These pours are scheduled for night of Thursday, August 5 (beginning at midnight) and the night of Thursday, August 12, also beginning at midnight. There may be some temporary noise and/or light during these nights while the crews pour concrete.
 
Court six at Boulder Mountain and courts one and two at the Trailhead will not be affected, as their upgrades are scheduled for 2022.
 
 
Last updated August 3, 2021.
New Amenity Access Cards
New Amenity Access Cards
 
New and more secure amenity access cards are here, and our system is live!
 
 
Last updated June 29, 2021.
Fire Mitigation
Fire Mitigation
 
On May 27, the Board approved a proposal from DLC Resources to perform fire mitigation in the common areas. The work is scheduled to begin on August 16 and will take about four months to complete. The following enclaves are scheduled for 2021:
  • Founders Ranch
  • Grayfox
  • Mountain Village
  • Pinnacle Hills
  • Silverhawk
  • Sonoran Hills
  • Terraces
  • Windsong
For more information about Las Sendas' fire mitigation plans, the Firewise USA designation, and what you can do to protect your property, click here.
 
Last updated June 11, 2021.
Asphalt Work
Asphalt Repair and Reconstruction
 
The Las Sendas Community Association Board of Directors has approved plans to repair roads, fill cracks, reconstruct streets, and seal asphalt. If your enclave will be affected, you will receive enclave-specific email communications.
 
 
Last updated June 29, 2021.
Playground Shades
Playground Shades
 
Shade for the Trailhead and Sonoran Heights playgrounds was approved in 2020 along with the proposal for the new equipment. Since then, the Association management had concerns about a lack of proper documentation for the warranty that needed to be resolved before the shades were installed. When scheduling the work, the contractor learned that the equipment required for the footings could not be transported to the site; thus, new plans had to be engineered. 
 
The type of cover requires precise engineering and measurements. To ensure a perfect fit, the manufacturer will not fabricate the covers until the posts are installed and measured. Therefore, the posts will be installed about 6-8 weeks before the shade cover is placed on topThe project is tentatively scheduled for completion in mid-August. Our contractor is trying hard to expedite the work. Thank you for your patience!
 
Last updated July 13, 2021.
New Mailboxes
New Mailboxes
 
This fall, seven more enclaves will be receiving brand new, more secure mailboxes. Below are the installation dates for the remainder of this year's project. If your mailbox is being replaced, you'll receive a letter via USPS and an email in advance.
 
  • Grayfox                                 Friday, August 27th   
  • Rolling Hills                            Thursday & Saturday, September 16th & 18th
  • Silverhawke                            Friday & Saturday, October 22nd & 23rd                              
  • Sonoran Heights                     TBD
  • Sonoran Hills                          Saturday, September 25th
  • The Highlands                         Thursday & Saturday, September 2nd & 4th
  • The Terraces                           Thursday, October 7th
 
Last updated August 3, 2021.
Tree Trimming
Enclave Tree Trimming
 
Tree Trimming within the enclaves ("behind the gates") is currently underway.  Storm activity may delay the schedule, as fallen and damaged trees and cacti are prioritized ahead of tree trimming maintenance. 
 
Last updated July 13, 2021.
Common Area Wall Painting
Common Area Wall Painting
 
After obtaining bids for the 2021 painting project, we learned that current prices are significantly higher than budgeted. Not only do these costs affect payments from the Association's reserve account, but they also affect homeowners directly, since residents are responsible for reimbursing the Association 50% of the cost to paint the wrought iron on their walls (where applicable). At the June 24 meeting, the Board decided to defer the 2021 painting project until 2022 or until costs go down.
 
Once the Board decides to move forward on this project again, the common area walls for the following enclaves will be scheduled to be repainted:
  • Black Rock
  • Legacy Hills
  • Mountain Gate
  • Stonecliff
  • Trailridge
  • Preserve
  • Pinnacle Hills  
  • Golf Colony
  • Granite Preserve
 
Last updated July 2, 2021.
Windsong Pool Deck Resurfacing
Windsong Pool Deck Resurfacing
 
A proposal to resurface the Windsong Pool Deck has been approved. The pool will be closed from August 16 through August 30.
 
Last updated July 27, 2021.
Looking for something else? Feel free to give us a call during regular business hours at 480-357-8780.